Project overview
Modernization of the client's owned digital ecosystem, content operations model, and analytics instrumentation.
Scope
Digital audit, content operations model, platform architecture, measurement plan, governance model.
Hours allocated
900
Hours used
402
Remaining
498
Staffed capacity
78%
Hours burn45%
Delivery
Timeline & milestones
AuditJun 1, 2026 — Jul 24, 2026
ArchitectureJul 27, 2026 — Sep 11, 2026
RolloutSep 14, 2026 — Jan 15, 2027
- Digital auditJul 24, 2026 · Complete
- Platform architecture sign-offUnstaffedSep 11, 2026 · In Progress
- Governance handoffUnstaffedNov 13, 2026 · Not Started
Resourcing
Team
| Team member | Role | Allocated hours |
|---|---|---|
| P. Nakamura | Digital Strategist | 200 |
| H. Adeyemi | Analytics Lead | 130 |
| S. Okafor | Project Manager | 70 |
Project health
72/ 100
Scope80
Rollout scope pending confirmation.
Timeline74
Architecture sign-off tight.
Budget / Hours82
45% used at 44% elapsed.
Capacity60
Strategy support short by 12 hrs/week.
Milestones68
Two milestones unstaffed.
Risks
- Strategy support under-allocated by 12 hours per week.